Frazer
& Tabberer were heavily involved, alongside Laing O'Rourke,
on the following project.
Customer:
Anglian
Water
Contractor
Laing O'Rourke
Site
Location
Barrow
to Stonewall
Date:
April 2001
A single steel water main to replace 21" ductile
iron and 21" cast iron mains between Barrow and Stonewall,
Lincolnshire, was installed.
The two iron mains had corroded along a 1.5km stretch,
and bursts and blow outs were resulting in unacceptable
water losses, and difficulties with regards to repairs.
A better long term solution had to be found. After
careful consideration of the alternative pipe materials,
especially with regard to the aggressive soil conditions
and elimination of pipe corrosion in the future, FT Pipelines
steel pipe with 3mm 3 layer PE coating, Copon 162 PWX
internal lining, and E joint ends was chosen.
The E joint end connections mean that there is no need
for any repairs to the internal lining after the pipes
have been welded together.
Any
information regarding Environmental Aspects or Health & Safety risks
should be directed through the Frazer and Tabberer IMS Systems.
dfrazer@frazerandtabberer.co.uk