Steel Pipes Case Study

Dartford Park Scheme - Thames Water (Case Study)

Frazer and Tabberer’s pipeline division FT Pipelines has completed delivery of materials into Dartford Park near Littlebrook Power Station for Thames Water.

Customer:  Thames water
Contractor McAlpines / McNicholas
Site Location Dartford Park, Little Brook Power Station
Date: February 2006

The two smaller diameter pipe quantities (300mm and 450mm) were supplied direct from F&T stocks whilst the 600mm was new rolled for the scheme. Additional to the straight pipes were a number of fittings including bends and spool pieces with NP16 flanges and gaskets.

FT Pipelines spent time assessing the material requirements with Alfred McAlpine and sub-contractor McNicholas to establish the exact requirements.

F&T then brought the elements of the project together which involved nine supply companies from five countries, providing a single point of contact for the client.

 


F&T included site visits for Canusa training and QA documentation to back up the material supplied. The construction during January and February of 2006 was completed ahead of schedule.

 

 

or click here to return to Steel Water Pipe

  
Any information regarding Environmental Aspects or Health & Safety risks should be directed through the Frazer and Tabberer IMS Systems.  dfrazer@frazerandtabberer.co.uk

© 2005 Frazer and Tabberer limited
  
Tayberry House, 6 Riland Industrial Estate, Sutton Coldfield, Birmingham, B75 7BB

tel: +44 (0) 121 311 2606  fax: +44 (0) 121 311 1218 e-mail: enquiries@frazerandtabberer.co.uk

 

home | steel pipe | locking lids | canusa heat wrap | pipe-finder | faq's