Frazer and Tabberer’s pipeline division
FT Pipelines has completed delivery of materials into
Dartford Park near Littlebrook Power Station for Thames
Water.

 |
Customer: |
Thames
water |
| Contractor |
McAlpines / McNicholas |
| Site
Location |
Dartford
Park, Little Brook Power Station |
| Date: |
February 2006 |

The two smaller diameter pipe quantities (300mm and
450mm) were supplied direct from F&T stocks whilst
the 600mm was new rolled for the scheme. Additional
to the straight pipes were a number of fittings including
bends and spool pieces with NP16 flanges and gaskets.
FT Pipelines spent time assessing
the material requirements with Alfred McAlpine and sub-contractor
McNicholas to establish the exact requirements.
F&T then brought the elements of
the project together which involved nine supply companies
from five countries, providing a single point of contact
for the client.

F&T included site visits for Canusa training and
QA documentation to back up the material supplied. The
construction during January and February of 2006 was
completed ahead of schedule.